Depot Junction report 4 – 4th April 2011

Ongoing work continues on the depot point access track, Formwork was applied around the new installed track drain. Mesh was applied ready for concreting. Formwork was also applied around the throw over leaver frame to finally enclose this in concrete to rail head.

Two cubic meters of concrete was purchased to complete the cess area in the western side of the depot track from the rail to rock wall and complete the base of the new track drain northern track train on the depot points. Three additional cubic meters of surplus concrete was supplied by Concrite.

Further excavation continues on the utilities trench heading south beyond Pole 22.

Regards

Danny Adamopoulos
Rail Infrastructure Manager

tram
Reinforcing mesh is applied on the corner to prevent cracking on the corner slab. Image taken facing west.

tram
Concrete is being poured up the Cess on the western depot track. Image taken facing South.

tram
Concrete is vibrated into place. Image taken facing south.

tram
Concrete beyond the reach of the shoot is wheel barrowed in to place. Image taken facing North.

tram
Track drain area and track drain base is finished off. Image taken facing West.

tram
Concrete is being barrowed in to place around the point throw over leaver. Image taken facing South West

tram
Completed and floated to finish the cess area on the depot track. Image taken facing South.

tram
Finished western Cess area and point leaver area. Image taken facing North.

tram
Utilities trench continues to be excavated south past pole 22. Image taken facing South.