Depot Junction report 2 – 19th March 2011

Ongoing work continues on the depot point access track, The track drain was formed up and the track was leveled for concreting. Six cubic meters of concrete was laid and finished in the 6 foot, as well as linear meter along the western side of the points and the rock wall. Heavy rain started to fall just as the pour was finalized. We improvised with the building of a temporary shelter over the concrete so it could be leveled and finished.

The heavy rain also highlighted a blocked drain which was quickly unblocked.

Due to the rain no other work was able to be undertaken

Regards

Danny Adamopoulos
Rail Infrastructure Manager

tram
Depot access track ready for concreting. Image Taken facing North.

tram
Track drain with Formwork applied ready for concreting

tram
Depot access track ready for concreting leveled and aligned. Image taken facing South.

tram
Concrete being discharged in the track. Image courtesy of Matthew Geier

tram
Last section of 4 foot of the track and surrounding drain is filled with concrete. Image courtesy of Matthew Geier

tram
Concrete being leveled off and screeded prior to finishing. Image taken facing North.

tram
A cover was erected over the concrete to keep the rain off so it could be trowel finished. Image taken facing South courtesy of Matthew Geier

tram
Concrete being screeded and finished prior to being covered over with Sheets of colourbond to keep the rain off. Image Courtesy of Matthew Geier

tram
New southern track drain located prior to the depot points serving its purpose, intercepting the run off from down the hill, during the heavy downpour. Image taken facing south

tram
Southern Track drain showing flow of water being drained away. Image taken facing East.